Results: |
6
Palletech System configurations were evaluated based on the following:
 | Total Process Time |
 | Machine Center Utilization |
 | Operator Utilization |
 | Rail-Guided-Vehicle Utilization |
A detailed report was published on the results, findings, and
recommendations provided with a high degree of confidence on the expected
results. The analysis eliminated in excess of $750,000 in capital investment. |