Results: |
Before modeling for improvements, the current rate for carriers per hour was
46. Color change rates were in excess of 700 per 8-hour day. Rework was
planned at approximately 30 percent. After building the model to establish
the "baseline" process, a scheduling methodology was created and tested for
a prime shift period. The results produced a minimum of 54 carriers/hr. with
a maximum of 103 carriers/hr. and an average of 78 carriers per hour. There
were 445 color changes and rework reduced to approximately 18 percent.
|