Determine the requirements to increase Earned Hours / Total Hours worked by
20% for 4 plating lines at the Hamilton Street Plating Process facility.
Results:
The
existing process required 3 dedicated operators for each plating line. STC
developed computer models of the existing process lines and identified the
solution necessary to achieve the current and forecasted production
requirements with fewer operators. The model indicated that the production
requirements could be achieved by dedicating 1 operator for each plating
line and using 5 floating operators to support any of the 4 plating lines.
This resulted in an annual Labor Savings of $335,000.